Major works
UPD
We had a meeting on site. Here is the summary of the meeting that emailed to Karen at Lewisham Homes:
Dear Karen, please see the summary of the meeting, which took place on 5/02/2018, below. If you have anything to add, please let me know.
Kat.
Summary of the meeting on 5/02/2018, Standlake Point block, SE23-2XB
Attended:
Kat, leaseholder, flat X, Standlake Point
X, leaseholder, flat X, Standlake Point
X leaseholder, flat X, Standlake Point
X leaseholder, flat X, Standlake Point
Karen Sweeney – Assistant contract manager for Lewisham Homes
Kiley Marr – construction project officer for Lewisham Homes
2 representatives from Breyer, works contractor
1 representative from Ridge, property and construction consultants
Reason for the meeting: clarification of the list of works proposed for the planned major works, S8-3S, Standlake Point, SE23-2XB
Discussed at the meeting:
-
smoke vent windows are proposed to be replaced with aluminium vents - leaseholders say there is no need to, all vent windows are in good order, also they were installed during last major works and leaseholder have already been charged/paid for the replacements in the past.
-
east and west side canopies - suggested by leaseholders: as an alternative, to enclose the areas to stop people urinating there, leaseholders insist Lewisham Homes to choose the cheapest option
-
leaseholders pointed out that wall tiles and floor tiles in the lobby are in good order and there is no need to replace them
-
leaseholders pointed out that a lot of works on the list are cosmetic works (protective mesh, removal of water tanks, lobby wall and floor tiles, floor steps cover to reduce noise, etc) and it is a waste of public and leaseholders money
-
a revised version of the list of works will be available for leaseholders to examine, however it was pointed out that it would be a goodwill gesture from Lewisham Homes; the leaseholders disagreed and pointed out that the current list of works is a ‘guesstimate’ and not acceptable.
-
leaseholders will be issued with a separate letter to sign if they wish to change their separate balcony door, it was pointed out that flat windows and balcony doors should match
Also:
- report says: Spot 258, spot 969 – asbestos survey, total: £411.83
my comment: there was asbestos survey carried out already on 12/06/2015, job #4341242 – why repeating the survey again and making leaseholders pay twice? Or no survey took place on 12/06/2015 but leaseholders were charged for??
At the meeting: requested to see survey reports when they are completed, Lewisham homes agreed to show them for leaseholders to examine
- report says: Spot 1036 - specialist subcontractors used to carrying out repairs to existing asphalt paving prior to Procol application, quantity: 55 items, £15,743.45
my comment: we have 40 balconies in our block, where quantity 55 came from?
At the meeting: quantity 55 were suggested to include the communal balconies in addition to flat balconies but pointed out, by leaseholders, that communal balconies floors are concrete – the surveyor from Ridge was not aware of the latter
- report says: spot 827 – building notice fees, quantity: 409,5 (unit price £1), total £409,50
my comment: block has 40 flats, where 409,9 number came from??
At the meeting: clarified that it is 1 notice
- report says: #307703 – cladding: remove existing and renew with cellular cored PVC shiplap boarding, quantity 9,9sm
my comment: the block does not have cladding, it has external brickwork. Where is this 9,9sm cladding??
At the meeting: Leaseholder Kat was given answer before the meeting took place, at earlier date, that the cladding was on the tenth floor in communal area; Leaseholder Samir was given explanation, before the meeting, at earlier date, that the cladding was on the ground floor, under the canopy, next to the bin chamber. The answer at the meeting was that the cladding was actually on the roof of the block. Leaseholders requested to see photos, Lewisham Home representatives agreed to show photos for examination
- report says: spot 234,232, 233 – contingencies, total: 17, ranged from £500 per unit to £10,000 per unit; total: 33,45 units = £280,000
my question: what are those 33,45 units that cost £280,000???
At the meeting: contingencies were said to include security mesh on the south (back) side of the building, plus removal of 4 old water tanks (1mx1.5m) on the roof. It was pointed out by leaseholders whether or not the replacement of the mesh is needed and whether it will be cheaper to sand it and paint it. In respect to the old water tanks, photos of the tanks were requested to see in order to establish the need for their removal and agreed to be shown by Lewisham Homes. One photo of one water tank was shown and the water tank appeared to be in good order and did not show the need for the removal.
- report says: #436203 – door frame: rub down, prepare, apply coat of primer, one undercoat, two coats of gloss paint on external surface of metal frames; total quantity: 63.6 lm
my question: where are the metal door frames in quantity 63,6 lm?? All communal doors are wooden.
At the meeting: the surveyor was not sure, works explained to be frames under the east and west side canopies of not-in- use and boarded sheds on the ground floor outside.
- report says: 17.7.5 – floor covering: renew any size or type of noising to steps, quantity 110 nr, £1953.60
my question: where exactly 110nr are?
At the meeting: clarified to be all steps in communal areas on all floors, however, the surveyor was confused about their number, surveyor suggested their quantity needs reviewing
- report says: spot 348 – painting to masonry, quantity 1012 lm, £4,614.72
my comment: is it external or internal, how did you come to this amount?
At the meeting: clarified – external masonry strips between brickworks
- report says: #9.9.1 – prep&redec to external walls, flats: painting to masonry, total: 563sqm, £3124.65
my question: the outside walls of the block are made of bricks, which is around 95% of the external walls, where 563sqm came from??
At the meeting: clarified – all flat balconies ceilings and walls, ground floor outside
- report says: #9.9.3 – prep&redec to external walls, flats: painting to timber surface, total: 114sqm, £1277.21
my question: there is no timbers on external walls, where are the timber surface on the external walls in our block exactly??
At the meeting: no answer received, the surveyor did not know, possibly ground floor shed doors, further clarification will follow
- report says: #9.9.5 – prep&redec to external walls, flats: wash down with detergent, total: 551,93 sqm, £1225,28
my comment: why external surface needs to be washed with detergent??
At the meeting: clarified – ground floor outside in front of the building under the canopy – walls, ceilings, supporting posts prior painting, however, the quantity suggested needs to be reviewed
- report says: # 9.12.8 – prep&redec to fences and railings: open type:painting to metal fences 1-1.5m high, total: 1491m, £39720.24
my question: we dont have 1491m of fence around our block, where this figure came from??
At the meeting: clarified – communal railings, flat/balconies railings, stairs, however, the quantity has to be reviewed, it does not appear to be right
- report says: #17.5.8, #17.5.2 – specialist treatment – apply anti-graffiti paint, total 1203.1 sqm, £16025.17
my qestion: we dont have problem with graffiti in our block, never was an issue, no need for anti-grffiti paint, why on the list of works???
At the meeting: the current state of the internal painting in the block is good, it was acknowledged by the surveyor that some spots require repairs and repainting. It was also confirmed the internal communal walls had been already painted with anti-graffiti paint in the past, leaseholders questioned whether it is needed to paint walls again with anti-graffiti paint
- report says: #43551 – surfaces: apply anti-graffiti paint to vulnerable external surface of brickwork, concrete, timber, total: 1070sm, £9616.09
my question: there is no problem with graffiti on external parts of the block, why on the list of works?
At the meeting: the surveyor was not sure where the area for painting was, further clarifications will follow
- report says: #435501 – clean existing graffiti covered surface, apply high pressure hot water to remove all traces of remover, paint, debris, total: 1070sm, £12380.97
my qestion: there is no graffity covered surface, where exactly 1070sm are covered with graffiti that you are prepared to spend £12380.97 for???
At the meeting: no graffiti found on external or internal walls, the surveyor was not sure where the area to be washed was, further clarification will follow.
- report says: #436205 – door: rub down, prepare for and apply one coat of primer, one undercoat and two coats of gloss paint on any size single metal door, quantity: 40.58 IT, cost: £2416.38
my comment: we dont have metal doors except for the main entry door and caretaker door which are in good order, where 40.58 It came from??
At the meeting: the surveyor did not know the answer, further clarification will follow
- report says: #135001 – meter cupboard: renew or fix new approved meter cupboard…complete with locking device…quantity: 4, cost: £261.30
my comment: I have no problem with my meter cupboard, why am I charged for smbd’d cupboards?? Also, one of this 4 cupboards have different price from another 3. Why?
At the meeting: meter cupboards in communal areas for some flats
- reports says: #070115 – shed door: renew any type of hasp, staple…or other equal and approved padlock to shed or bin doo, supply two keys…quantity:20, cost:£467.97
my question: sheds are not in use, I dont use any shed why am I charged for the lock??
At the meeting: the surveyor did not know that the sheds were boarded, further review and clarification will follow, sheds are not in use
- report says:# 070107 - shed door: renew shed or bin store door with any size softwood framed, ledged, braced door, quantity: 20, cost £3769.79
my comment: sheds are not in use, I dont use any shed, why am I charged for it?
At the meeting: the surveyor did not know that the sheds were boarded, further review and clarification will follow.
- you report says: #324125 – door: overhaul external door and frame and fanlight complete, remove all ironmongery, piece out, make good, resecure beads, architraves, rehang door, ease, adjust, reglaze fanligh, quanity 1, cost £106.23
my comment: it is recently changed door, nothing wrong with it, why you charged massive amount to replace the door and now you repairing it?
- report says: 11.35.0 – repair of PVCu windows/doors: doors: ease, adjust, lubricate hinges, fittings, quantity; 25, cost: £555
my comment: we dont have communal PVC doors, if they are doors to flats, why am I charged for somebody’s else door?? My door is wooden.
At the meeting: clarified – flat doors for council flats only, not leaseholders
- report says: 17.10.4 – replace door to caretaker store, quantaty: 1, cost £205.35
my comment: the caretaker’s door is fairly new, it is in good order, why replacing it??
At the meeting: the caretaker’s door, outside, witnessed by all attended, was in good order and fairly new: no replacement is needed.
- report says: #16.21.5 – renew door and frame with PVC door and frame, quantity: 75, cost: £ 26556.74
my comment: what doors are they? If flat doors to balconies, there are 40 of them, all communal doors are wooden and there are about 20 of them (10 to stairs, 5 on south and north sides each), why do they need replacement?? Where quantity 75 came from??
At the meeting: the surveyor did not have an explanation, the quantity 75 appeared to be incorrect, the quantity will be reviewed.
- report says: spot 1041 – standard upgrade of integrated reception system, quantity: 40, cost £5063.20
my comment: IRS has been renewed during the last major works, it was charged lots of moneys for basic fanctions, why we are charged again for the upgrade when the good IRS should have been installed in the first place??
At the meeting: the works are for the communal aerial, it is one communal aerial, not 40. It was pointed out that leaseholders do not use Sky and dont require an upgrade.
- report says: 14.1.0 – CCTV survey of drain runs, quantity 16, cost: £1332
my comment: CCTV survey of drains were done on 9/06/2015, job # 4340705 – wasn’t it good enough or was it done at all? Why to do it again?
At the meeting: the surveyor did not know that CCTV survey has been recently done, so no need to do it again
- report says: spot 420 – lightning conductor works at 1st tower block at Woodvale, quantity: 1, cost: £1713.97
my comment: why are we charged for works in the block at Woodvale?? We are Bampton Estate!
At the meeting: confirmed it is one lightning conductor per block and the job was a duplicate. Spot 381 has already included works with the lightning conductor. The job spot 420 should be taken off the list.
- report says: 8.19.0 – re-pointing in masonry: existing brickwork: repointing areas exceeding 3.0sqm, quantity: 23sqm, cost: £714.84
my comment: where are these 23sqm? Where is the problem with the brickwork?
At the meeting: the area in question was not found
- report says: 101907 – wall: cut out bricks from face of the wall, clean and clear away, lay up to 15No new facing bricks in cement lime mortar, bond, bed, point to match existing, quantity: 75it, cost: £2106.15
my comment: where are the bricks that need replacemen? 2106.15 pounds to replace 75 bricks???
At the meeting: the area in question was not found
- report says: 6.12.51 – general repairs: former hopper and chute, quantity:10, cost £512.79
my comment: waste chutes were already renewed during last major works, why do it again??
At the meeting: the majority of works were planned to upgrade the bin chamber. Pointed out by leaseholder that there is no need for the upgrade. The bin chamber has metal doors and always locked - no problem with safety.
- report says: 6.12.34 – take down satellite dish and re-fix it, quantity: 58, cost £8,369.40
my comment: I dont have any satellite dish, why am I charged for it??
At the meeting: confirmed – there is one communal aerial for residents to use, no private satellite dishes are meant to be on the roof. It was pointed out that leaseholders don’t have satellite dishes and should not be billed for.
- report says: 029305 – supply standard NO BALL GAMES sign, screw to timber, quantity: 55, cost £3260.77
my comment: the building has 4 external walls!!! Where 55 signs came from???
At the meeting: 55 signs - all signs for the block, not only NO BALL GAMES; it was pointed out that the signs in the block have been recently replaced and leaseholders were billed for them. The current signs are new and dont need to be replaced. This works leaseholders should not be billed for.
Hi Karen, in additiin of the summary, some things were missed for the record:
-
the surveyor was checking the works sheets for Radcot Point when aswering questions, not Standlake Point. When the leaseholder pointed it out to him, the surveyor said that it is the same.
-
Electrical works include replacent of emergency lights. It was pointed out by leaseholders that some communal lights have been replaced with emergency ones and not all communal lights need to be replaced.
-
Painting meter cupboards in communal areas - leaseholder pointed out that they are in good state and dont need painting
Kat